§ MR. BUTCHER (Cambridge University)To ask the First Commissioner 2071 of Works why the building operations for the extension of the British Museum in Montagu Place have, so far as the main structure is concerned, been suspended for nearly eighteen months; and when they are likely to be renewed.
(Answered by Mr. Harcourt.) The first contract for the lower storeys was completed in the autumn of 1907. The interval which has occurred between the completion of the first contract and the commencement of the second contract for the superstructure is due to protracted negotiations between the architect and the engineer which were necessary to the preparation of detailed drawings and specifications. Tenders have now been received for the superstructure and are under consideration. As soon as I am able to accept a tender the work will proceed forthwith.