HC Deb 25 January 1956 vol 548 c197
39. Mr. Dodds

asked the Minister of Transport and Civil Aviation what progress has been made in the construction of the Dartford-Purfleet Tunnel; and what part of the work is expected to be carried out this year.

Mr. Watkinson

The overhaul of the existing plant and equipment is nearly completed. Tenders have been invited by 29th February for the main tunnelling work, but I cannot give any useful estimate at this stage as to future progress.