§ 2. Mr. Walker-Smithasked the Minister of Works how far there is uniformity in respect of the form of building contract used in connection with work for the various Government Departments.
§ Mr. StokesAll the principal Government Departments placing building contracts use the standard General Conditions of Government contracts for Building Works (Forms CCC/Wks/1 or 2).
§ Mr. Walker-SmithIs it possible in any cases, if it is so desired by the contractor, for the standard form issued by the Royal Institute of British Architects to be used in this type of work?
§ Mr. StokesNo. We could not adopt that without considerable alteration.