HC Deb 23 July 1946 vol 425 c1846
2. Mr. William Shepherd

asked the Minister of Works what has been the average time taken for the erection of temporary houses, including the time required for the preparation of the site.

The Minister of Works (Mr. Tomlinson)

From the beginning of site preparation to the occupation of the house, the average time taken has been about nine months. The period is being reduced as the rate of supply of certain items improves.

Mr. Shepherd

Can the right hon. Gentleman say how this time compares with the estimate originally given?

Mr. Tomlinson

No, I cannot.

Major Legge-Bourke

Can the right hon. Gentleman say what period is involved when the sites are prepared and no work is going on, before building commences?

Mr. Tomlinson

In that period of nine months that I have given, about three months.