HC Deb 02 November 1938 vol 340 cc194-5
23. Commander Marsden (for Mr. Crowder)

asked the Minister of Transport what progress is being made with the scheme for the creation of a twin roadway across Hartford Bridge flats; when he expects the work will be commenced; and what is the approximate estimate of the time of construction?

Mr. Burgin

It is hoped to obtain entry upon all the land required for the improvement of the trunk road across Hartford Bridge flats by March, 1939. The works will probably take 12 months to complete.