§ Mr. ASHLEYasked how many torpedo boat destroyers were provided for in the Estimates for 1908–9; and when were they laid down?
§ Mr. McKENNASixteen torpedo boat destroyers were provided for in the Estimates for 1908–9, and they were laid down as follows: March, 1909, 4; April, 1909, 8; and May. 1909, 4.
§ Mr. ASHLEYCan the right hon. Gentleman say why all the destroyers were not all laid down in the financial year?
§ Mr. McKENNAThey were all ordered unusually early in the financial year. When the contractors laid them down was not a matter for us, provided they are completed in the contract time.
§ Mr. ASHLEYAnd what is that time?
§ Mr. McKENNAI think it must be within 21 months; I cannot say exactly.