§ MR. BOLAND (Kerry, S.)I beg to ask the Chief Secretary to the Lord Lieutenant of Ireland whether he can state when the application for the building of a new school at Lettir, near Glenbeigh, County Kerry, was first submitted; on what date was the information conveyed to the manager that, owing to the drawing up of new plans for national schools, the building could not be proceeded with; and whether he can now say that building operations can be commenced at Lettir, so that the school will be ready for use before next winter.
§ MR. WYNDHAMThe application was received in January, 1899; the necessary forms of particulars were not, however, completed by the manager until May, 1901. In March, 1902, a grant was conditionally sanctioned. In respect to the concluding inquiry I would refer to my reply to the next Question on the Paper.