Environmental Impact Assessment (Amendment) (Northern Ireland) (EU Exit) (No. 2) Regulations 2019 Work package
A work package focussed on the Environmental Impact Assessment (Amendment) (Northern Ireland) (EU Exit) (No. 2) Regulations 2019, made available on 19 February 2019, subject to the Made negative procedure.
There are 10 business items actualising 13 steps.
Business items which have happened - Business items which do not have a date
Business items which have happened
-
15 February 2019
-
Instrument created
Read at www.legislation.gov.uk | Business item details
-
Instrument made (signed into law)
Read at www.legislation.gov.uk | Business item details
-
-
19 February 2019
-
Laid before the House of Lords (House of Lords)
-
Laid before the House of Commons (House of Commons)
-
-
4 March 2019
-
Considered by the Secondary Legislation Scrutiny Committee (SLSC) (House of Lords)
No comment by the Secondary Legislation Scrutiny Committee (SLSC) (House of Lords)
-
-
20 March 2019
-
Considered by the Joint Committee on Statutory Instruments (JCSI) (House of Commons and House of Lords)
Instrument drawn to the special attention of the Houses by the Joint Committee on Statutory Instruments (JCSI) (House of Commons and House of Lords)
Joint Committee on Statutory Instruments (JCSI) draws the special attention of both Houses to this instrument on other grounds (House of Commons and House of Lords)
-
-
30 March 2019
-
Objection period ends
-
Instrument remains law
Read at www.legislation.gov.uk | Business item details
-
Procedure concluded in the House of Commons and the House of Lords (House of Commons and House of Lords)
-
Business items which do not have a date
-
Instrument comes into force as law
Read at www.legislation.gov.uk | Business item details