HC Deb 15 March 1990 vol 169 c349W
Mr. Wigley

To ask the Secretary of State for Wales what was his original planned timetable for the construction of the Penydip tunnel on the A55 near Penmaenmawr together with the original estimated cost of this tunnel; and what is the latest timetable and estimated project cost.

Mr. Wyn Roberts

The decision to proceed with a tunnel on the present alignment was taken in 1985. "Roads in Wales 1985" indicated that the estimated gross cost at November 1984 prices was £31.32 million and work was programmed to start between January 1988 and December 1990. Work on the four-year contract started in November 1989, at which time the estimated gross cost of the scheme was £79.4 million at October 1989 prices.