HC Deb 26 November 1974 vol 882 c154W
Mr. David Price

asked the Secretary of State for the Environment if he will give his current estimate, section by section, of when the various sections of the M27 motorway will be opened to the public.

Mr. Carmichael

The contract completion dates for the sections of the M27 motorway which are at present under construction are as follows:

  • Cadnam-Ower, April 1975;
  • Ower-Chilworth, June 1975;
  • Windhover-Funtley, December 1974;
  • Funtley-Portsbridge, June 1975.

It is too early yet to say when the sections between Chilworth and Windhover and between Havant and Chichester are likely to be built.