§ Motion made, and Question proposed, That this House do now adjourn.—[Mr. Clelland]
10.28 pm§ Mr. Nigel Waterson (Eastbourne)I am delighted to have the opportunity to raise an issue of massive importance to my constituency and to East Sussex. It is of no small importance to those of my colleagues who made the trek to Eastbourne recently for what the press deemed to be our bonding session. It is a great pleasure to see the Minister in her place, with her minder.
The importance of the issue to East Sussex is borne out by the presence in the Chamber of my hon. Friend the Member for Bexhill and Battle (Mr. Wardle) and my right hon. Friend the Member for Wealden (Sir G. Johnson Smith). I have also had a note from the hon. Member for Hastings and Rye (Mr. Foster). Almost all parties are united by the need for a variety of improvements to our local roads. I know, for example, that my right hon. and hon. Friends and the hon. Member for Hastings and Rye feel strongly about improvements to the A259 and related schemes. I pay special tribute to our former colleague, Tim Rathbone, who was Member for Lewes until the general election and a doughty fighter for the road schemes about which I am going to talk.
The first scheme involves the A27 between Lewes and Polegate. My preference would have been for complete dualling of that stretch, which is a massive traffic bottleneck. After much investigation, the previous Government produced a scaled-down project involving three schemes: the A27 Wilmington bypass, the Selmeston bypass, and the Southerham-Beddingham improvement. In his announcement of the scheme the then Minister responsible for roads noted:
The A27 is a vital artery for Sussex.How right he was. Had those improvements been pushed forward, they would have not only increased dramatically the road's effectiveness for business and tourism but made it a much safer carriageway for local people and visitors.In a letter about the A27 to a local paper, the then county engineer stated:
There are significant safety gains to be made from the provision of a modern dual carriageway",which was all that the scheme involved and which would have produced an accident rate of approximately one third of that of the present single carriageway. The scheme would also have addressed all substantive environmental objections to the original A27 plans. As far as I can tell, that scheme lies a long way ahead and may have to wait for the next Conservative Government to see the light of day.This evening I want to concentrate on the Polegate bypass, which in turn was part of the Weald and Downland design, build, finance and operate scheme. As the Minister will know from her briefing, the bypass is not a new idea but was envisaged before the war. Polegate is no longer in my constituency. In its wisdom, the boundary commission moved it into Lewes. The routes that go through Polegate are vital to my constituents. There are almost always major traffic problems in and near Polegate. The road is vital to our local road system, linking it to the M23, M25 and the port of Newhaven. 222 Those wider connections are the reason for the presence of my right hon. and hon. Friends and of the hon. Member for Hastings and Rye. The issues go far wider than just Polegate.
I have taken delegations to meet more than one Minister. Most recently, in early July I took a delegation of constituents to meet Baroness Hayman to go through the issues. We represented a wide range of bodies: all the local authorities without exception; business organisations, including Sussex Enterprise; and representatives of the tourist industry, which is, of course, very important in our part of the world. That was backed up by hundreds of letters from large employers and others.
I pay tribute to Councillor Peter Wallis, chairman of the transport and environment committee in East Sussex county council and his excellent director Mr. Bob Wilkins, both of whom have been very supportive of my efforts and those of my colleagues.
In a recent document which was available to Baroness Hayman, East Sussex county council made the following point:
Proposals to develop a Polegate bypass have been inextricably linked from the very beginning with the construction of the A22 new route from the A27 at Dittons to Seaside, Eastbourne as part of an overall strategy for the Eastbourne area.It says that in the public inquiries over the scheme the inspector made it clear thatthe Orders for the A22 should be confirmed unless the Polegate Bypass was removed from the National Roads Programme.The new A22 route in my constituency, that would take traffic from the industrial areas and the Sovereign Harbour area of Eastbourne up to Dittons Corner by Polegate, is a major road project costing £28 million which is nearing completion. If it linked up with the Polegate bypass, if that were built, there would be considerable benefits for the area. According to the county council, there would be immediate benefits of some 1,500 jobs in the new business parks in the Eastbourne Park area as part of the Eastbourne borough plan. As the county council points out, these sites are currently landlocked and need to be opened up by the development of the new route.High-quality office developments will create about 1,000 jobs in Sovereign Harbour, the new marina development incorporating many berths for yachts, houses and in due course shops and a hotel. There is also the possibility of commercial development.
It is no exaggeration for the county council to say:
The strategy for sustainable development in East Sussex would be fundamentally undermined if the proposed trunk road improvements in the county associated with the Weald and Downland Network DBFO package were now to be withdrawn … Such a decision would have a devastating impact on the county's prospects for economic recovery.We need a dual carriageway paralleling the south coast between the A23 and the A21.The improvements are supported by every local authority in the area and by Sussex Enterprise. The Polegate bypass scheme had gone through all its statutory stages and was ready to start construction at the time of the general election. The Polegate bypass must be a dual carriageway as it not only carries east-west traffic around Polegate, but north-south traffic into Eastbourne.
Hon. Members can imagine my concern and that of the councils involved and many residents in the area when, as part of the Government's roads review earlier this year, 223 it was decided that the scheme would be put on hold at least until next spring and possibly would never see the light of day. As the county council said, that would have a devastating impact on the area.
I have received hundreds of letters of support for the project and expressions of disappointment and distress at its suspension or possible cancellation. A company called T. Cox & Son Ltd. wrote:
The cancellation of a new A27 Lewes to Polegate trunk road was a major consideration in our decision to relocate … from Eastbourne to Tonbridge.One of our major local employers, Anglo Dutch Meats, employing more than 300 people, wrote:We have continued to invest in the area because of the previous Government's commitment to improving the road system. However, if this commitment is now not to be honoured, we will be forced to consider relocation of our factories which will result in an increase in unemployment for Eastbourne and Hastings.
§ Mr. Charles Wardle (Bexhill and Battle)May I assure my hon. Friend that his important message will be endorsed by every sensible thinker in the county? May I link with his remarks about Polegate the importance of the Hastings eastern and the Hastings western and Bexhill bypasses and, with them, the Marsh road link over the Pevensey levels? Those matter to local development as well as to through traffic to and from the channel tunnel.
§ Mr. WatersonMy hon. Friend is absolutely right—this is a seamless robe of projects that hang together.
Another letter I received came from the leading surveyors and valuers Stiles Harold Williams and referred to one of its clients. The letter states:
I think there is little doubt that until the Bypass is built our client's development, which has planning consent which would create 250-500 permanent jobs will not go ahead.Just to show that there is almost total unanimity on the subject of the Polegate bypass, I have a press release issued by Councillor Roy Martin, who is not only town mayor of Polegate and someone with whom I have worked from time to time, but a leading local Liberal Democrat. He writes:I now consider it is time for the silent majority in Polegate who are concerned about the lack of a dual carriageway By-Pass around the town to relieve the intolerable noise, vibration and air pollution problems experienced by residents, to speak up.I entirely agree with that.
§ Sir Geoffrey Johnson Smith (Wealden)I should add that those in the industrial estates to the north of Eastbourne have told me in strong terms that they regard it as a bad decision to postpone these improvements, seemingly indefinitely.
§ Mr. WatersonMy right hon. Friend and I have received correspondence on this subject from many of the same companies.
I have three important questions for the Minister. First, how much compensation is being paid, or is to be paid, to the successful contractors—money that could be spent on the bypass itself? I have seen a variety of figures quoted. The Times, referring to the Paymaster General, spoke of
a compensation bill of more than £6 million".224 A local newspaper quoted a figure of £143 million, but I believe that that covers all the projects that were put on hold at the same time. Both are amazing figures, nevertheless.Secondly, does the Minister accept that there are substantial benefits for the local communities from the project going ahead? On that subject, it is interesting to see the document attached to the very press statement announcing the Minister of Transport's decision on 28 July. On safety, that document states:
Improvements in standards of routes have been forecast to bring accident savingsand on environment, it states:Lamberhurst Bypass, Polegate Bypass and the A259 Hastings schemes would remove through traffic from settlements"—settlements being that rather unsatisfactory word used to mean places where people live.Thirdly, when can we expect a decision? I know that the Government are all about rolling programmes of reviews and more reviews, but sooner or later—surely—there has to be a decision. Originally, we were told that the review would be completed by next spring, yet, only last week in the Sussex Express, fears were expressed that
a decision on the Polegate bypass could be further delayedbecause of an announcement by the Minister of Transport, who said thatthe Polegate scheme is one of eight 'case studies' to be reappraised in an attempt to find a better way of taking decisions on new roads.I can tell the Minister a better way, which is to take a decision of some sort.In conclusion, the Minister must be aware from all the representations, letters and other documents that she and her colleagues have received that there is anger and disappointment, which I share, among my constituents on this subject. It is no good fobbing us off with talk of yet another review. We need the Polegate bypass now. If we do not have it now, first we shall have contractors who will be paid not to build it; secondly, we shall have spent £28 million of taxpayers' money on the new A22, which ends in the middle of a field—the biggest and most expensive cul de sac in Europe and a monument to the Government's inability to make decisions; and, thirdly, my constituents will face ever more job losses in a shrinking local economy, not to mention a massive inconvenience to both local residents and visitors to the area. Furthermore, my constituents living along or near the existing A22 can expect no improvement whatever—indeed, a deterioration—in both road safety and the local environment.
I urge the Minister to give us some hard indication tonight that that project and the whole of that DBFO scheme will be taken out of the review and initiated so that work can start as soon as possible.
§ The Parliamentary Under-Secretary of State for the Environment, Transport and the Regions (Ms Glenda Jackson)Before I respond to the hon. Member for Eastbourne (Mr. Waterson), may I offer my apologies to you, Mr. Deputy Speaker, to the whole House and particularly to my hon. Friend the Member for Don Valley (Caroline Flint) for my failure to be present in the House for last night's Adjournment debate. I can offer neither excuse nor reason, simply my most humble apologies. 225 I thank the hon. Member for Eastbourne for raising these important issues, and for being so generous in affording time to his hon. Friends on issues that are clearly important not only to Eastbourne but to East Sussex. I also thank him for setting his concerns on infrastructure improvements in East Sussex strongly and clearly within the context of community needs, regeneration and safety.
I understand the hon. Gentleman's desire for early decisions on the schemes that he mentioned, but he will know that the Government have embarked on a fundamental review of transport policy. This is not a "fobbing off' exercise. Our objectives are for a strong economy, a sustainable environment and an inclusive society. As he pointed out, transport is a vital part of all those aims.
The backdrop to our fundamental review is a candid recognition that we need a shift in direction. Revised national road traffic forecasts published last month show traffic increasing by nearly 40 per cent. over the next 20 years. If current policies continue, congestion will get worse, the impact on the environment will be even more severe, and those who have no access to private transport will find it even more difficult to get around.
We must develop an integrated transport system that makes the best use of the contribution that each mode can make; ensures that all options are considered on a basis that is fair and is seen to be fair; and takes into account, from the outset, considerations of accessibility, integration, safety, the environment and the economy. Above all—I have little doubt that the hon. Gentleman will agree with me here—an integrated transport system must be sustainable. One of the encouraging aspects of what is, indeed, an ambitious task is the degree of consensus on the need for change.
It is a feature of the policy development work now under way that we are involving a wide range of external advice and expertise, including local authorities, business, trade unions, transport professionals and transport users. That is the context for the roads review, examining the role that trunk roads should play in an integrated and sustainable transport policy. Against the background of increased congestion, we have three broad options for roads: first, to make better use of existing infrastructure; secondly, to manage demand; and thirdly, to provide new infrastructure.
To make best use of existing infrastructure is the obvious first choice. It has been provided at substantial cost in both financial and environmental terms, and we must make the best use of that investment. Technologies old and new can help in making better use of our roads network. A number of measures can also bring safety benefits, and we will need to ensure that these are given proper priority. We need, however, to be realistic about what the various options can deliver.
We must also look seriously at other harder options: managing demand and providing new infrastructure. Managing demand is a vast topic. It encompasses reducing the need to travel, by land use planning for example, an assessment of the extent to which a shift to other modes can be encouraged, and inevitably the question of controlling demand by pricing or rationing mechanisms.
226 At a local level, many local authorities are seeking, by means of integrated transport packages, to combine these measures, so that mobility is maintained but adverse consequences of that mobility are reduced.
The Highways Agency's programme of small safety schemes is continuing, but major new construction is under review. Providing new infrastructure is a very difficult option, financially and in terms of the impact that it may have on the environment. Our starting point is that we shall not proceed with major new road construction unless we are satisfied that there is no better alternative; even then, there will be difficult choices to be made within the limited resources available.
There is no substitute for rigorous case-by-case examination of the options. Volume II of our consultation document "What Role for Trunk Roads?" sets out, region by region, the perceived traffic problems and the roads programme inherited from our predecessors.
§ Mr. WardleAs my hon. Friend the Member for Eastbourne (Mr. Waterson) has already asked, how long is all this likely to take?
§ Ms JacksonWe have given a clear commitment that the White Paper, which will be fundamental to our policy for integrated transport, will be published early next year.
The existence of a scheme in the inherited programme is seen as prima facie evidence that there is a transport problem. We are seeking from our regional consultations a view on whether these are the most important problems or whether others deserve greater priority. We envisage two outputs from that part of the review: a firm, short-term investment programme and a programme of studies to consider the remaining problems out of which the medium and long-term investment programme will emerge.
The Government office for the south-east has held three day-long seminars as part of our consultation process on integrated transport. A seminar in Ashford on 14 October considered transport corridors in the east of the region, including the south coast route and north-south routes between the M25 and the south coast.
Points that the hon. Member for Eastbourne has made about the importance of the Polegate bypass, the improvements between Lewes and Polegate, and other trunk road schemes in terms of safety, regeneration, environmental relief and integration with local transport investment and land use planning objectives, were strongly made at that seminar, and we shall be taking those views into account along with the written and other representations that we have received.
I recognise the importance of the A22 scheme from Dittons to Eastbourne town centre in terms of the relief it provides to the existing A22 and the access it affords to expanding commercial and industrial areas. However, we cannot allow a decision on the Polegate bypass to be driven by this alone. Should the bypass not go ahead, we would, of course, need to consider alternatives with the Highways Agency and local authorities.
The hon. Member for Eastbourne and other hon. Members, including my hon. Friend the Member for Hastings and Rye (Mr. Foster), have also supported other schemes, which, together with the Polegate bypass, made up the Weald and Downland DBFO—design, build, finance and operate—project, considered this summer as 227 part of the accelerated review. I take the opportunity to offer an assurance that the points that he and others made will be fully taken into account in the current review.
The hon. Member for Eastbourne mentioned some local concern at the announcement that the Polegate bypass scheme is one of eight case studies being analysed as part of a project to develop a new appraisal framework. The aim is to define a method capable of looking at all potential solutions to transport problems, and identifying options that best meet the objectives of integration, accessibility, safety, economy and environmental impacts. The purpose is to develop a new appraisal methodology rather than to study a specific case per se. The Polegate bypass is one of the eight because it was felt to be a good example of its type, and had already been studied in some depth.
Developing a forward-looking integrated transport policy that supports a strong economy, contributes to a sustainable environment and helps to create a just and inclusive society is, as I have said, a huge challenge. 228 Through the work now under way on trunk roads, we want to achieve a robust short-term programme and a system for planning future investment in the road network—whether measures to make better use of the existing network or to provide new infrastructure—which is fair and seen to be fair, which allows a proper opportunity for all concerned to make their contribution, and which looks at transport problems squarely in the context of an integrated strategy.
Of the three questions that the hon. Member for Eastbourne posed, I trust that I have covered the last two. However, if he believes that I have failed to respond to some issues in detail, he should write to me, and I shall be happy to reply. As to compensation, all bids will be reviewed on their merits. The amounts to which he referred are mere speculation. We are examining such bids and, as I said, they will be reviewed on their merits.
§ Question put and agreed to.
§ Adjourned accordingly at five minutes to Eleven o 'clock.