HC Deb 07 July 1975 vol 895 cc16-7
14. Mr. Grist

asked the Secretary of State for Wales if he will give the latest estimated date for the completion of the M4 motorway; and if he will make a statement.

Mr. Barry Jones

About 30 miles should be under construction by the end of the year, and most of the motorway should be completed by the end of 1977, but the Bridgend Northern bypass and the Castleton-Coryton sections are unlikely to be finished before late 1979. The section between Baglan and Lonlas is in the initial stages of preparation and it is too early to forecast a completion date.

Mr. Grist

Is the Minister aware that there is a cynical view in South Wales that this completion date is for ever receding into the distance? When may we expect the results and findings of the inquiry into the section bypassing Cardiff?

Mr. Barry Jones

I think that the hon. Gentleman's cynicism is a little misplaced. The inspector's report on the Castleton to Coryton section has been received by my Department.

Mr. Nicholas Edwards

Does the Under-Secretary agree that the date has slipped back under successive Governments and that it is disappointing that it is now even later? Can he give us any date for the completion of the extension work on the Carmarthen bypass and the dual carriageway to St. Clears, which is of equal importance to my constituency and to developments which may take place in the Celtic Sea?

Mr. Barry Jones

I take on board the importance of any development in the Celtic Sea. We envisage the terminal point of the M4 at Pont Abraham and a much improved road to St. Clears on the A40 and A48.