§ 27. Mr. Wellbelovedasked the Minister of Public Building and Works what progress has been made on that part of the East-West Highway in Nepal being built by his Department on behalf of the Ministry of Overseas Development.
§ Mr. John SilkinOf the 75 miles due to be constructed, 30 miles of forest have been cleared and surveyed and 1106 approximately 12 miles are under construction.
§ Mr. WellbelovedWill my right hon. Friend tell the House whether British construction equipment is being used on this project?
§ Mr. SilkinIt is, in very considerable quantity. The value of British equipment used here is £300,000. Other materials are obtained from either Nepal or India or from the United Kingdom.