HC Deb 01 December 1969 vol 792 c903
27. Mr. Boyden

asked the Minister of Technology what progress is being made with the erection and leasing of the two advance factories in the West Auckland area.

Mr. Varley

Both advance factories, one of 25,000 sq. ft. and the other of 10,000 sq. ft., are under construction and are expected to be completed in March and February, 1970, respectively. Applications have been received for both and negotiations are proceeding.

Mr. Boyden

Can my hon. Friend say how many male jobs are likely to arise in these two factories?

Mr. Varley

I cannot give precise information, but I believe that there will be a high proportion of male jobs in these two factories.