HC Deb 08 May 1967 vol 746 cc1051-2
29. Mr. Chapman

asked the Minister of Health when the new Page Street wing for Westminster Hospital will now definitely be completed; what was the agreed completion date in the building contract; what are the reasons for the delay advanced by the contractors; and what services of the hospital are being hindered by this delay.

Mr. K. Robinson

The answer to the four parts of the question are: by mid August, according to present estimates; 19th July, 1966; variations to the scheme; a number of diagnostic, treatment and teaching services must carry on in limited accommodation.

Mr. Chapman

Is my right hon. Friend aware that the hospital is satisfied that the variations from contract are very minor, and do not justify a delay of this length? Is he further aware that it is probably due to the lack of efficiency of this firm—Tersons—and will he black-list it from future hospital contracts until it improves its efficiency?

Mr. Robinson

It is also my understanding that the number of variations to the scheme is not an excessive one for a scheme of this size. Where cases of undue delay in the completion of hospital contracts are brought to my attention I take note of these together with other relevant factors when advising on the letting of other hospital contracts.