HC Deb 19 April 1967 vol 745 c563
42. Mr. George Jeger

asked the Minister of Transport what progress has been made in the preparation of plans for the Thorne by-pass and the construction of a new bridge over the canal there.

Mr. Swingler

I hope the final plans of the Thorne by-pass, which will include a bridge over the canal, will be available shortly. The preparation of the draft Scheme can then go ahead.

Plans for a possible temporary bridge in Thorne are being discussed with the town council.

Mr. Jeger

Can my hon. Friend say what progress is being made with the promised aerial survey of the district?

Mr. Swingler

Considerable progress is being made. I am sorry that there have been inevitable delays because of getting the alignment with the Doncaster south by-pass correct. So there have been temporary difficulties, but we now hope to go forward with the scheme very rapidly, and we hope to establish a temporary bridge.