HC Deb 17 February 1965 vol 706 c1185
32. Mr. Clark Hutchison

asked the Secretary of State for Scotland what is the additional cost of the Tay Road Bridge over the original estimate; and if the building programme is up to time.

Mr. Ross

I am informed by the Joint Board that the cost of completing the scheme may be about £51 million as compared with the Provisional Order estimate of £4.386 million. To this must be added the interest which will accrue on loans advanced during the construction period. There is a good prospect that the bridge will be ready for the target date of June, 1966.