§ 31. Mr. Swinglerasked the Minister of Transport If he will state, for each motorway so far constructed, his original estimate of the cost of the land required, the actual price paid, and the total figure by which his estimates have been exceeded on account of the higher cost of land.
§ Mr. GalbraithWith permission, I will circulate a table of motorway land costs in the OFFICIAL REPORT. I regret that it would not be possible to calculate how much of the total increases of costs over estimates is attributable to higher land values without a disproportionate expenditure of time and labour.
§ Mr. SwinglerIs the Minister aware that he did this for me in the case of the M.6 and it worked out that an extra £500,000 had been added to the estimate on account of higher land prices? Would he and the Minister therefore investigate this matter, because there appears to be good evidence that there is profiteering at the nation's expense?
§ Mr. GalbraithIf the hon. Gentleman looks at the figures which are to be circulated, he will see that there is a lot more in land costs than just the price of the land. For example, there is the new basis of valuation and compulsory purchase under the 1959 Act. Sometimes additional land is required for hard shoulders, as for example on the M.1. Often there are wide and unforeseeable variations in the payments made for disturbance. All that is reflected in the land cost. But it is not necessarily the price of the land.
§ Mr. SwinglerIs the Minister aware that my Question clearly asks what is the higher price which the Ministry has paid—which came to £500,000 in the case of the M.6—compared with what was estimated? That is the answer in which we are interested and may we have it?
§ Mr. GalbraithIf the hon. Gentleman looks at what I propose to circulate in the OFFICIAL REPORT, I think he will find that it answers his Question.
§ Following are the figures:
LAND COSTS OF CONSTRUCTED MOTORWAYS | ||
— | Estimate before negotiations began | Cost of Acquisition |
£'000 (a) | £'000 (a), (b) | |
M.1 London-Crick (Northants) | 211 | 774 |
M.10 St. Alban's By-pass | 80 | 251 |
M.2 Medway Towns Motor Road | 225 | 311 |
M.20 Maidstone By-pass | 89 | 59 |
M.4 Slough By-pass | 48 | 220 |
Maidenhead By-pass | 75 | 91 |
M.5 Lydiate Ash-Twyning | 175 | 238 |
M.50 Ross Spur | 72 | 172 |
M.6 Lancaster By-pass | 120 | 66 |
Preston By-pass | 98 | 133 |
Lancashire Section | 448 | 698 |
Staffordshire Section | 198 | 304 |
A.1(M) Doncaster By-pass | 106 | 114 |
Stevenage By-pass | 35 | 98 |
Totals | 1,980 | 3,529 |
(a) Neither estimates nor costs cover accommodation works, reinstatement of fences, etc. | ||
(b) Where final settlements have not yet been made the latest estimates have been included. |
§ Note.—In addition to higher land values other factors have contributed to the increases such as:—
§ (i) New basis of valuation for compulsory purchases (Town and Country Planning Act, 1959).
§ (ii) Certificates of alternative development (Town and Country Planning Act, 1959).
§ (iii) Additional land required, e.g. M.1 hard shoulders.
§ (iv) Obligation to buy whole properties.
§ (v) Wide and unforeseeable variation of payments for disturbance.