HC Deb 21 November 1962 vol 667 c1201
27. Mr. Watkins

asked the Minister of Transport what reply has been sent to the representations made by Brecon-shire County Council about the delay in the construction of the Heads of the Valley Road, on the section Gilwern to Brynmawr; and whether he is satisfied that the contractor is employing sufficient labour and machinery for the work.

Mr. Marples

The county council has been informed that delay in completion of the road is due to weather and other conditions which entitle the contractor to an extension of time under the contract. It is hoped that, as a result of a concentration of effort, the contractor will be clear of the difficult section in the Black Rock area of the Clydach Gorge by the New Year thus relieving the present traffic conditions there. In view of the importance which I attach to the completion of this scheme as soon as possible, I am watching the position closely to ensure that the work progresses as quickly as weather conditions permit. I am advised that as much labour and machinery is now on the site as could usefully be employed during the winter months.