HC Deb 09 November 1960 vol 629 c1029
48. Mr. Freeth

asked the Minister of Transport when he hopes to begin work on the flyover at the junction of A.30 and A.33.

Mr. Hay

I am afraid we have not yet been able to fit this scheme into our programme.

Mr. Freeth

Does not my hon. Friend recall that last Session he gave a hopeful answer about the construction of this flyover? In view of the delays which have taken place on this dangerous road junction, would it not be a good idea to ask the county council to prepare plans so that when it can be fitted in, it will be all ready to go into construction?

Mr. Hay

Yes, Sir. We are getting on with this. We have now reached general agreement with Hampshire County Council on the form which the flyover should take. The council will be asked to start the necessary survey work so that the necessary detailed procedures can be put in hand. Until the survey is completed I cannot forecast the starting date.