§ 10. Mr. Langford-Holtasked the Minister of Transport and Civil Aviation whether he will make a statement on the progress being made on the London to Birmingham motorway.
§ Mr. WatkinsonProgress is well up to schedule. Site clearance is almost complete, as well as about 25 per cent. of the excavation and 20 per cent. of the drainage. Work has started on about half the bridges, and most of the 150 miles of temporary fencing has been put up.