§ 29. Mr. Malcolm MacMillanasked the Secretary of State for Scotland the value and mileage of road of works completed or started under the Crofter Counties road programme between 1945 and 1951 throughout the Outer Hebrides; and what works directly under this scheme have been started between May, 1951, and May, 1957, in this area.
§ Mr. N. MacphersonI shall, with permission, circulate in the OFFICIAL REPORT detailed information about all the Crofter County schemes in the Outer Hebrides started between 1945 and 1957.
§ Mr. MacMillanWill the Joint Under-Secretary kindly say whether he can answer the second part of the Question now?
§ Mr. MacphersonIf the hon. Gentleman will study the Answer, he will find that only one scheme was started before 1950 and no schemes were completed before 1953.
§ Mr. MacMillanIs the reply much the same as it was as regards houses, that nothing has been done about Crofter Counties scheme roads since 1951?
§ Mr. MacphersonThe answer is that none of these schemes were completed before 1953 and reconstruction has been started in 1956 and 1957.
§ Following is the information:
§ Hebrides, and what was the estimated cost in 1951.
§ Mr. N. MacphersonThe estimated cost of building the North Ford Causeway, based on the accepted tender, is £452,000. In 1949, when a preliminary 15 survey was carried out by the consultants, they estimated the cost roughly at £160,000.
§ Mr. MacMillanHas the Joint Under-Secretary yet managed to draw the glaring conclusion that, as with housing, roads and everything else, it is sheer folly to put off transport schemes of this kind where they are essential and where costs have been trebled through the folly of so-called economies?
§ Mr. MacphersonThe figures are not really comparable. The original survey was only a preliminary one. The design of the causeway and bridges has had to be modified as a result of trial borings and investigations into the effect of the tides.