§ 16. Mr. E. Johnsonasked the Minister of Transport and Civil Aviation for how long work was held up on the Loughton 895 by-pass on route A.5, while the beams for the bridge, which had to be constructed, had to be redesigned owing to the inadequacy of the original design; and what total extra cost will have been incurred on account of this delay.
§ Mr. WatkinsonIn this case the contractors have an outstanding claim against the county council for compensation in respect of delay to the progress of the works. Until this has been disposed of, I do not think I should make a statement on the points to which my hon. Friend refers.
§ Mr. JohnsonIs my right hon. Friend aware that this delay was aggravated by the fact that the county surveyor had to refer even minor matters to his Ministry? Is he further aware that the extra cost involved was in no way the fault of the contractors concerned, but was due to the methods of bureaucracy?
§ Mr. WatkinsonOn the broad issue, if my hon. Friend can give me any suggestions which will help to speed up road construction, I shall be only too pleased to consider them, but this specific case is sub judice as far as I am concerned.