§ 53. Mr. John MacLeodasked the Minister of Transport to give a list of the road work being carried on at the present time under the Crofter Counties Scheme.
Mr. BraithwaiteThe following works are in progress: The reconstruction of the bridges at Strathan, Strathkanaird and Drumrunie on the Ullapool-Drumrunie Road; the improvement of about five 1727 miles of the Tarbert-Rodel Road, north of Rodel; and the improvement of the Portree-Staffin road.
§ Mr. MacLeodCould not the Minister see that this scheme was restarted? It was a completely false economy to cut this Crofter Counties Scheme, and the Government are ill-advised to follow the misapplied cuts that were made by the previous administration.
Mr. BraithwaiteThe works included in my reply represent a total cost of £121,886. About 50 per cent. of this scheme has been completed, and to carry out the remainder would cost between £8 million and £9 million, for which funds are not at present available.
§ Sir D. RobertsonDoes the Minister realise that skilled road men have been paid off in the Highland counties in the last few weeks while essential repairs to dangerous roads remain undone?