§ 22. Lord Malcolm Douglas-Hamiltonasked the Minister of Transport when the new jetty at Kyle of Lochalsh will be completed.
§ Mr. BarnesNo acceptable tenders as regards either cost or time of completion were received for the construction of a new slipway according to the original plans. In order to secure the improvement of the ferry service this summer it was accordingly found necessary to prepare an amended scheme for an extension of the existing slipway to enable the ferry to be used at low tide. Every effort will be made to have the extension usable for Skye week. Further work will be done later to make the slipway more convenient.
§ Lord Malcolm Douglas-HamiltonIs the Minister aware that a Railway Executive official recently stated in a letter that this slipway would be completed this spring, and that if he is to 14 get it ready by this summer he will have to get a move on?
§ Sir T. MooreThat is too much to expect.