HC Deb 28 July 1933 vol 280 cc2950-1
6. Mr. TINKER

asked the First Commissioner of Works if he can give an approximate date when the refacing and repairing work now in progress on the Houses of Parliament will be completed?

The FIRST COMMISSIONER of WORKS (Mr. Ormsby-Gore)

It is anticipated that the work will be completed in 1941.

Mr. TINKER

May I draw the right hon. Gentleman's attention to the fact that visitors are getting the impression that this is a permanent structure, that it is always going to remain; and will he hurry on the work even if it requires extra labour to get it done?

Mr. ORMSBY-GORE

When we have done the main work, which I hope will be a long time before 1941, there will still be a lot of small details, but the appearance to the general public will not be as bad as this year and next year.

Sir DOUGLAS NEWTON

Cannot more labour be employed and the work completed at an earlier date?

Mr. ORMSBY-GORE

It is entirely a question of working in economic units. There were strong representations last year that we should not do what my hon. Friend suggests and try to crowd it in, but that we should work in economic units, with a more or less fixed number of skilled men—they are very largely skilled men—and with fixed units in size of material and the rest of it.

Mr. McENTEE

Can the right hon. Gentleman tell us what the approximate estimate will be?

Mr. ORMSBY-GORE

I gave that the other day: in all, from when we began to repair till the end, three-quarters of a million.

Mr. MANDER

Can my right hon. Friend say in what year it will be necessary to start repairing the work that is now being done?