HC Deb 02 May 1927 vol 205 c1280
73. Sir FREDRIC WISE

asked the Secretary of State for Air the cost to date of the Cardington works and the estimated future cost to complete the works?

The SECRETARY of STATE for AIR (Sir Samuel Hoare)

As the answer includes a number of figures, I will, with the hon. Member's permission, circulate it in the OFFICIAL REPORT.

Following is the answer:

On the assumption that what my hon. Friend wants is the cost of the works services at Cardington involved in the airship development scheme of 1924, the answer is £155,800, made up as follows:

£
Alterations to airship shed 100,000
Mooring mast 50,000
Cost of water supply and electrical equipment 5,800
£155,800

Of the above sum, £147,800 has been actually expended; the balance of £8,000 will be expended on completion in the current year.

As regards further expenditure, I would refer the hon. Member to page 32 of current Estimates where full particulars are given.