HC Deb 15 November 1926 vol 199 cc1518-9
18. Mr. RHYS

asked the Secretary of State for the Colonies whether satisfactory progress is being made with the construction of the harbour at Takoradi, in the Gold Coast; and how much of the main and lee breakwaters are now complete?

Mr. AMERY

The answer to the first part of my hon. Friend's question is in the affirmative. At the end of September, 6,210 lineal feet of the main breakwater, out of a total of 7,631, and 2,420 lineal feet of the lee breakwater, out of a total of 4,749, had been constructed.