HC Deb 23 November 1925 vol 188 c901
44. Mr. ROY WILSON

asked the Secretary of State for the Colonies whether the Takoradi harbour will be completed within the time and at the cost stipulated in the estimate given in 1924 by the engineer now in charge of the work; and, if not, what revised estimate has been submitted?

Mr. AMERY

The estimate has had to be revised in the light of fuller information as to local conditions, and the estimated total expenditure is now £3,066,000 and the contract date for completion! 31st December, 1928.