HC Deb 02 July 1923 vol 166 c14
13. Mr. BECKER

asked the Under-Secretary of State for the Colonies if any progress has been made this year towards harnessing the latent water power in Palestine under the Rutenberg Concessions; and has any electrical energy been produced?

Mr. ORMSBY-GORE

Yes, Sir. I am informed that considerable progress has been made under the Auja Concession, which, as the House is aware, is the only concession that has actually been granted. Power house, cables and transformers have been installed and net-work erected in Tel Aviv and Jaffa, where the current is now available. In anticipation of the supply, 225 applications for connections had been received in Tel Aviv and Jaffa up to 28th June, including many from Arabs. Supply of current began on 28th June.

Captain Viscount CURZON

Can the hon. Gentleman say whether the machinery was installed by British or by foreign firms?

Mr. ORMSBY-GORE

It was installed by the Rutenberg Company.