HC Deb 01 March 1911 vol 22 cc350-1
Mr. BURGOYNE

asked whether the battleship cruiser "Indefatigable" was commissioned for service prior to the completion of her official acceptance trials; and, if so, whether this is in accordance with the general practice?

Mr. McKENNA

The "Indefatigable" has been commissioned. Although the principal trials have been completed, the final acceptance trial of the machinery has not yet been carried out. This is not in accordance with the general practice, but minor modifications in the machinery fittings required prior to final trial have made the departure from general practice desirable in this case.

Mr. BURGOYNE

Are we to understand that the engines have been opened and examined prior to acceptance and Commission?

Mr. McKENNA

Yes, I understand it is only in regard to some minor defects of the machinery fittings that the delay in the final trial has taken place. Perhaps the hon. Member will give me notice of any further questions on this point.