HC Deb 03 June 1892 vol 5 cc538-9
MR. SEXTON (for Mr. TIMOTHY HEALY,) Longford, N.

I beg to ask the Secretary to the Treasury whether the original estimate for the Greystones Harbour, County Wicklow, by the Engineer of the Board of Works, was £10,000; that, to make up this sum, the Piers and Harbours Commissioners, under the Act of 1883, 46 & 47 Vic. c. 26, made a free grant, out of the £250,000 granted by that Act, of 88,500, and that the balance was made up according to the Report of the Inspectors of Fisheries for 1890 by a contribution of £500, and a loan secured by the locality of £1,000; while, according to the Return to Parliament, dated 5th April, 1892, No. 153, the expenditure on this harbour was £17,870, and a further sum of £2,087, estimated to complete the works, making a total of nearly £20,000 instead of £10,000 as originally contemplated; and was this additional £10,000 given as a free grant out of the £250,000; and, if so, has it been made on the recommendation of the Piers and Harbours Commissioners, to whom the allocation of this £250,000 was entrusted by the Act of 1883, or were they consulted in the matter; and, if not, on whose authority has it been done?

*SIR JOHN GORST

The original sanction was for £10,000 — namely, £8,500 free grant, £1,000 loan, and £500 local contribution. An expenditure of £2,957 over the estimate was authorised by the Treasury on the 16th December, 1889. The erection of the north groyne, a separate work not at first contemplated, was authorised by the Treasury in August, 1890, at a cost of £7,000, from the balance of the Sea Fisheries Fund, with the concurrence of the Irish Government. The Piers and Harbours Commissioners ceased to exist under the Act 52 & 53 Vic. c. 71, so that the further expenditure was not incurred on their recommendation.