HC Deb 20 June 2003 vol 407 c512W
Mr. Hancock

To ask the Secretary of State for Defence (1) what the expected(a) cost and (b) commissioning date is of the Meteor BVRAAM missile; and what estimates were made when the contract was let; [110347]

(2) what the expected (a) cost and (b) commissioning date are of the Swiftsure, Astute and Trafalgar submarines; and what estimates were made when the contracts were let; [110351]

(3) what the current expected (a) cost and (b) commissioning date is of the Bowman Communication System; and what estimates were made when the contract was let; [110345]

(4) what the (a) cost and (b) expected commissioning date are of Watchkeeper; and what estimates were made when the contract was let; [110352]

(5) what the expected (a) cost and (b) commissioning date is of the Eurofighter; and what estimates were made when the contract was let; [110346]

(6) if he will make a statement in relation to the (a) cost and (b) expected commissioning date of the (i) light forces anti-tank guided weapon system, (ii) Nimrod MR A4 aircraft, (iii) A 400M aircraft and (iv) the ASRAAM missile; and what estimates of both were made when the contracts were let. [112060]

Mr. Ingram

The information requested is shown in the following table: