HC Deb 21 November 2002 vol 394 c262W
Mr. Gordon Prentice

To ask the Secretary of State for Transport when he expects the channel tunnel rail link to be fully operational; and if he will make a statement. [82551]

Mr. Jamieson

Section 1 of the CTRL (channel tunnel to Fawkham Junction, north Kent) is now over 90 per cent. complete and on target for completion by the end of 2003. Section 2 of the CTRL (Kent to St. Pancras in London) is over 30 per cent. complete on target for opening in early 2007.