HC Deb 18 July 2002 vol 389 c458W
Mrs. May

To ask the Secretary of State for Transport, pursuant to his answer of the 10 July 2002,Official Report, column 981W, on London Bridge railway station, if he will define the intended output given in his 10-year plan for additional capacity at London Bridge, at paragraph 6.72, page 71; and if he will make a statement. [70559]

Mr. Jamieson

Railtrack's proposals for the Thameslink 2000 project include scope to raise the number of services calling at London Bridge to eighteen an hour in each direction, with the operation of 12-car trains.

I would refer the hon. Member to my answer of 11 July 2002, Official Report, column 1113W where I stated that the public inquiry Inspector's report into Railtrack's proposals is currently under consideration in the office of the Deputy Prime Minister.