HC Deb 29 November 2001 vol 375 c1059W
Mrs. May

To ask the Secretary of State for Transport, Local Government and the Regions which phases of the infrastructure upgrades on the East Coast Line have so far been(a) started and on what date and (b) completed and on what date; on what dates the subsequent phases of the upgrades are due (i) to start and (ii) to be completed; and if he will make a statement. [17790]

Mr. Byers

[holding answer 23 November 2001]: Phase 1 of the project, which commenced in 1999, provides capacity improvements to the Leeds Station area and is expected to be completed by 2004–05. The Strategic Rail Authority is continuing to take forward project development work on the upgrade.