§ Mr. Matthew TaylorTo ask the Secretary of State for Defence if he will list the construction projects and work conducted at RAF Menwith Hill since 1 January 537W 1994 and paid for under the bilateral cost-sharing arrangement between the United Kingdom Government and the United States Government. [30470]
§ Mr. SpellarConstruction Projects at RAF Menwith Hill conducted under the bilateral cost-sharing arrangement for which detailed planning clearance has been sought and received since 1 January 1994 are listed
(1) Projects in progress or completed:
- Refurbish Water Tower
- Upgrade Sewage Works
- Replace Security Fence
- Bus Layby
- Relocate two Guard Towers and Erect one
- High Level Gantry to Cooling Towers
- Army and Air Force Exchange Service Mini Mall
- Chapel Extension
- Replacement Building 36H
- Erect Covered Walkway Building 25
- Building 20 Laundry Extension
- Shredder
- Provision Temp Classrooms
- Access Road
- Lighting Near Building 48
- Replacement Chain Link Fence (Interceptor 1)
- Provision Flammable/Chemical Storage
- Facility Support Contractor Additional Portakabins
- Erection All Weather Enclosure Armed Forces Network Antennas
- Spectator Seating Two Sportsfield
- Building 45 Entrance Porch
- Building 30 Compressor House
- Building 15 Community Centre Extension
- Building 21 Cafetorium Extension
- Automated Teller Machine
- Smokers Shelters
- Building 31A Pitched Roof
- Ops Security Lighting Esso 29 Radome
- Grapnel Radomes—infrastructure only
- Ops Support Buildings
- Building 25 Pitched Roof
- Building 45 and Castlemaine
- Portakabin adjacent Building 33B
- Dog Kennel and Handler Facility
- Skate Pad
- Building 17 Extension
- Nessfield Gate
- Youth Playground
- New High School.
(2) Projects cancelled:
- Construct Impound Car Lot
- Construct PC6.