To ask the Secretary of State for Defence if he will list the construction projects and work conducted at RAF Menwith Hill since 1 January 1994 and paid for under the bilateral cost-sharing arrangement between the United Kingdom Government and the United States Government. [30470]

Mr. Spellar

Construction Projects at RAF Menwith Hill conducted under the bilateral cost-sharing arrangement for which detailed planning clearance has been sought and received since 1 January 1994 are listed(1) Projects in progress or completed:

  • Refurbish Water Tower
  • Upgrade Sewage Works
  • Replace Security Fence
  • Bus Layby
  • Relocate two Guard Towers and Erect one
  • High Level Gantry to Cooling Towers
  • Army and Air Force Exchange Service Mini Mall
  • Chapel Extension
  • Replacement Building 36H
  • Erect Covered Walkway Building 25
  • Building 20 Laundry Extension
  • Shredder
  • Provision Temp Classrooms
  • Access Road
  • Lighting Near Building 48
  • Replacement Chain Link Fence (Interceptor 1)
  • Provision Flammable/Chemical Storage
  • Facility Support Contractor Additional Portakabins
  • Erection All Weather Enclosure Armed Forces Network Antennas
  • Spectator Seating Two Sportsfield
  • Building 45 Entrance Porch
  • Building 30 Compressor House
  • Building 15 Community Centre Extension
  • Building 21 Cafetorium Extension
  • Automated Teller Machine
  • Smokers Shelters
  • Building 31A Pitched Roof
  • Ops Security Lighting Esso 29 Radome
  • Grapnel Radomes—infrastructure only
  • Ops Support Buildings
  • Building 25 Pitched Roof
  • Building 45 and Castlemaine
  • Portakabin adjacent Building 33B
  • Dog Kennel and Handler Facility
  • Skate Pad
  • Building 17 Extension
  • Nessfield Gate
  • Youth Playground
  • New High School.
(2) Projects cancelled:
  • Construct Impound Car Lot
  • Construct PC6.