HC Deb 05 March 1996 vol 273 cc137-8W
Mr. Ingram

To ask the President of the Board of Trade what is the Government's responsibility for the decommissioning costs including site clearance costs of the experimental nuclear reactor previously operated by the Scottish universities research and reactor centre at the former national engineering laboratory site in East Kilbride. [18066]

Mr. Ian Taylor

[holding answer 4 March 1996]: Responsibility for the decommissioning of the experimental nuclear reactor at the Scottish Enterprise technology park at East Kilbride lies with the operator concerned, which in this case is the Scottish universities research and reactor centre.