HC Deb 03 November 1995 vol 265 c517W
Mr. Chris Davies

To ask the Secretary of State for Transport when tenders will be let for construction of the main carriageway of the M66 Manchester Outer Ring Road; and what is the reason for the delay. [39987]

Mr. Watts

[holding reply 30 October 1995]: There has been no unexpected delay. I hope to be in a position to award a contract for the first part of the remaining main carriageway, (Contract 1) around the turn of the year. Tenders for the second part (Contract 3) are yet to be sought.