HC Deb 07 February 1994 vol 237 c40W
Ms Mowlam

To ask the Secretary of State for National Heritage if he will publish the report of his Department's consultants Kennedy and Donkin into the British Library project; if he expects the completion date for the project set to be adhered to; and if he will make a statement.

Mr. Brooke

Construction of the first phase of the project is substantially complete. A start has been made on the final phase of construction, and its structural frame is 75 per cent. complete. This completion phase is on schedule and I do expect the building to be completed in 1996 as planned.

The handover of the first phase of the building to the library has been delayed, first by problems with the bookshelving and more recently by problems with the electrical wiring. The bookshelving problem has been overcome, at the contractors' expense, and the installation is now complete. The essence of the wiring problem is that inspections have revealed installed low voltage wiring with damaged insulation. Plans for rectifying the faults in the installation of the wiring are being agreed with the contractor concerned.

I do not propose to publish the Department's report commissioned from the consultants Kennedy and Donkin. It is a contractually sensitive document.