HC Deb 04 March 1993 vol 220 c234W
Mr. Harvey

To ask the Secretary of State for Transport what is the total value of the outstanding disturbance claims arising from the building of the A361 Tiverton to Barnstaple link road; and what he estimates to be the interest accumulated on this sum.

Mr. Kenneth Carlisle

The value of third-party claims arising from the construction of the A361 north Devon link road stages 2A and 2B would be difficult to quantify, as they are subject to negotiation between the claimant, the contractors, the consultants who supervise construction, and the Department. Compensation negotiated in respect of third-party claims does not attract interest.

Mr. Harvey

To ask the Secretary of State for Transport how many disturbance claims arising from the building of the A361 Tiverton to Barnstaple link road are still outstanding.

Mr. Kenneth Carlisle

The table provides a breakdown of third-party claims arising from the construction of the A361 north Devon link road stages 2A and 2B.

Number
Stage 2A
Claims received 58
Claims settled 54
Claims yet to be resolved 4
Stage 2B
Claims received 65
Claims settled 46
Claims repudiated 5
Claims on which no recent action has been taken by claimants 14