HC Deb 26 July 1993 vol 229 c626W
Mr. Cox

To ask the Secretary of State for the Home Department if he will list the building projects and their cost now being undertaken at Wandsworth prison as of 16 July.

Mr. Peter Lloyd

Responsibility for this matter has been delegated to the director general of the prison service, who has been asked to arrange for a reply to be given.

Letter from Mr. D. Lewis to Mr. Tom Cox, dated 26 July 1993: The Home Secretary has asked me to reply to your recent Question about the building projects, and their cost, now being undertaken at Wandsworth prison. After completion of the modernisation of D Wing in March 1993, at a cost of £5.5 million, enabling works are under way to allow the modernisation of C Wing. The enabling works (including the removal of asbestos and electrical wiring) will be completed in September 1993, at an estimated cost of £175,000. Work on the 15 month refurbishment of C Wing will then commence in September 1993, at an estimated cost of £7.15 million.