HC Deb 13 February 1992 vol 203 c631W
Mr. Barry Jones

To ask the Secretary of State for Wales if he will give details of his plans to improve road communications between north and south Wales.

Sir Wyn Roberts

The Government's policy is to continue to upgrade the A470 and A483 by means of selective improvements. Those in progress or planned on the north-south network are:

A470

  1. 1 Pentre Bach—Cefn Coed
  2. 2 Crew Pitch
  3. 3 Storey Arms Phase II
  4. 4 Storey Arms Phase III
  5. 5 Felinfach By Pass
  6. 6 Builth Wells By Pass/Llanelwedd Junction (is also part A483)
  7. 7 Smithfield Bends
  8. 8 Diversion East of Llangurig—Wern Villa
  9. 9 Carno Road Caersws
  10. 10 Commins Coch By-Pass
  11. 11 Improvements at Bwlch Oer Ddrws
  12. 12 Maes yr Helmau—Cross Foxes Phase I & II
  13. 13 Gelligemlyn—Llanelltyd Diversion Phase I & II
  14. 14 Ty Nant—Maentwrog Road Railway Station
  15. 15 Salem Place—Ty Mawr
  16. 16 Lledr Valley Improvements
  17. 17 Llanrwst By-Pass
  18. 18 Penloyn—Tanlan
  19. 19 Pentrefelin—Croesau
  20. 20 Llanbrynmair
  21. 21 Ffridd Fawr
  22. 22 Pentre Mawr
  23. 23 Tanyard Pitch
  24. 24 Irfon Bridge Bends (S of Newbridge on Wye)
  25. 25 Llandinam Village
  26. 26 Clatter Village
  27. 27 Caersws River Bridge

A483 (North of Builth Wells)

  1. 1 Brynsadwrn Bends and Bridge
  2. 2 Maes yr Abad—Wern Bridge
  3. 3 Welshpool Relief Road
  4. 4 Croesfoel Roundabout—Grade Separation
  5. 5 Newtown By Pass
  6. 6 Pant—Llanymynach By Pass (Welsh Section)
  7. 7 Side support, Llythddu
  8. 8 Glascoed and Bends
  9. 9 Howey Village By Pass