HC Deb 25 January 1989 vol 145 c574W
Dr. Marek

To ask the Secretary of State for Transport if he will give(a) the amount of finance made available in the form of grant or loans by the European Economic Community towards the construction of the M4 Severn bridge and (b) the total actual cost of construction, giving all figures at current prices.

Mr. Peter Bottomley

The United Kingdom was not a member of the EEC when the existing Severn crossing was constructed in 1961–66.

The cost of construction of the Severn bridge alone was £ 63.8 million, and the Severn crossing as a whole (including the Wye bridge linking viaducts);£ 102.3 million, both at current prices.

Back to