HC Deb 25 January 1989 vol 145 c574W
Mr. Nicholas Winterton

To ask the Secretary of State for Transport if there are any plans to improve the traffic flow on the A40 at the remaining road junctions in London; and if he will make a statement.

Mr. Peter Bottomley

Yes. Improvements are planned or under construction at the four remaining junctions on the A40 in London as follows:

Swakeleys Road An underpass is under construction and due for completion Spring 1990.

Long Lane Work is to start on construction of an underpass later this year.

Gipsy Corner Western Circus Draft orders proposing grade separation at these junctions were published in March 1988.