HC Deb 12 April 1989 vol 150 c603W
Mr. Steel

To ask the Secretary of State for Scotland if he will list the schemes approved and their expected completion dates for improvements to the A7 Edinburgh-Carlisle trunk road.

Mr. Rifkind

The major A7 schemes in the trunk road programme are the north Middleton diversion, the Dalkeith bypass and the Langholm bypass. Works started on the north Middleton bypass in March. Advance works on the Dalkeith bypass are expected to start in May or June and the main works in October. The contract period for both schemes is 24 months and they should therefore be completed during 1991. The Langholm bypass will not complete its statutory and design stages before the mid-1990s.