HC Deb 13 May 1987 vol 116 c214W
Mr. Peter Bruinvels

asked the Secretary of State for Transport why replacing signs and sign gantries on the M25-M23 interchange is likely to take six months; and whether he will consider a lane rental scheme for this work.

Mr. Peter Bottomley

The installation of new signs and gantries has to be carried out in stages if traffic flow is to be maintained. A shorter period would require further traffic restrictions.

A change to a lane-rental scheme now would involve additional cost and delay.