HC Deb 22 October 1986 vol 102 cc918-9W
Mr. John David Taylor

asked the Secretary of State for Northern Ireland when the present works commenced at the footbridge opposite Saintfields road Presbyterian church, Newtownbreda; when these works are due for completion; what is the objective of these works; and if he will make a statement.

Mr. Needham

This work began on 4 August 1986 and was completed on 18 September. The objective was to replace the bridge deck and end supports which were severely damaged in a traffic accident.

From the numerous inquiries received from local residents and representatives about the timing of repairs to the bridge and their concern for the safety of children, I am satisfied that there is a demand for the footbridge at this location.