HC Deb 06 February 1984 vol 53 c450W
58. Mr. Speed

asked the Secretary of State for Transport what are the anticipated dates and costs for improvement of the A20 road into London from the termination of the existing M20.

Mrs. Chalker

A preliminary contract for the Sidcup bypass is already in train and the main contract is due to start in the late Summer of this year. The works will take up to three years to complete, at an estimated cost of £42.6 million.