HC Deb 30 July 1980 vol 989 cc747-8W

(Note. The inquiry also concerned other matters including applications for water orders and licences.)

DOE costs to date—£26,000.

Time before inquiry commenced

NWWA APPEAL: 60 weeks from submission of planning application to lpa.

BNFL APPLICATION

38 weeks from submission of planning application to lpa.

Length of inquiry into all matters—57 sitting days.

Decisions will be issued as soon as possible after receipt of the inspector's report, which is awaited.

COIN STREET

THIRTEEN PLANNING APPLICATIONS

BY SIX APPLICANTS

(Note. The inquiry also concerned a compulsory purchase order).

DOE costs—£40,000.

Time before inquiry commenced—varied from eight to 36 weeks from submission of planning application to lpas.

Length of inquiry into all matters—83 sitting days.

Decisions announced 35 weeks after close of inquiry.